Stony Lake Camp Renovation

Write something about your church here.

Floor Trusses Are Set

January, 2018

01/12/18 Floor Trusses Set It was another cold and snowy Saturday, but a great crew showed up to complete the blockwork and start fitting the floor trusses. The door openings between the new sleeping rooms, the kitchen and dining areas were completed. Al Lake working on a s ..

Read more

Meeting

January, 2018

Camp Board & Crew Leaders meet for progress review I attended a meeting of the Stony Lake Camp/Renovation Committee and work crew leaders at Stony Lake Camp last night (Jan 4) on a cold and cloudless night. After a short walkthrough of the kitchen/dining construction area, they met i ..

Read more

Concrete Pour

January, 2018

Concrete poured The shortest day of the year was also one of the busiest as the important milestone of pouring the floor occurred. On Wednesday the plumbing inspection was completed and at 7 am the following day, the crew started backfilling the trenches and compacting the soil for the c ..

Read more

Plumbing is finished

December, 2017

12/19/2017 The blog postings are now online, so I can be a little more current as to project status. Progress appears to be slow when there are open trenches and temporary walls, but there are a lot of little things being worked on like temporary heating, rerouting of wiring and some ma ..

Read more

Excavation completed on east side and block laying

December, 2017

Post 6 In late November, the excavation was complete on the east side of the bulding where the new cooler/freezer room will be and it was block laying time. A temporary shelter was constructed to keep the elements out. The weather was nice enough for a few days to do the  ..

Read more

Work on Septic

December, 2017

Post 5 The Septic system is an important part of the project. The existing system had been failing and needed to be replaced. The new system will meet the needs of the camp for a long time.

 ..

Read more

Land cleared for bunkhouse and septic excavation

December, 2017

Post 4 Outside, the site prep work was progressing in late October. Trees cleared for the new bunk house will be taken to the mill and used in the construction of the future Pavilion. The east deck was partially removed to allow for excavation. Major exca ..

Read more

Interior walls are taken down

December, 2017

Post 3 Demolition of interior walls.

 ..

Read more

Kitchen gets cleared out

November, 2017

Post 2 While the demo work was starting on the main level, the lower level was a beehive of activity as all the kitchen materials and equipment were sorted for storage. It wasn’t long before everything movable was gone from the kitchen and dining areas.  ..

Read more

Organ Removal and Sanctuary Clearing

November, 2017

Post 1 Hello and welcome to the Stony Lake Camp Renovation Blog I will attempt to keep a running commentary on the activities at the camp during the 2017-2018 Renovation Project. Briefly, the project consists of two phases.  ..

Read more

Upcoming Events

Feb 22, 2018

2018 LLC Winter Services

Service Motto: "With God all things are possible" (Mark 10:27) Dates: February 22-25, 2018 Wednesday, February 21 7:00..

Jul 05, 2018

2018 LLC Summer Services

2018 LLC Summer Services Snohomish, Washington July 5 – 8 “Be still and know that I am God” (Ps. 46:10) Schedule Th..

SUBSCRIBE TO OUR NEWSLETTER

Receive promotions and news by email. Unsubscribe with one click.