Stony Lake Camp Renovation

Write something about your church here.

Trusses Go Up

June, 2018

Blog Post 062618 Trusses Go Up Friday the 22nd dawned cooler and drier than the previous weekend. By noon we had a couple workers on site to continue with the sheathing on the buildings and preparing for delivery of the trusses. At the main building, work continued on forming up the pat ..

Read more

Walls Go Up

June, 2018

First Walls Go Up I have no doubt that you are tired of hearing me say ‘it was a busy weekend at the camp’ and after this weekend, I will refrain from using it again (at least for awhile) as we had multiple activities going on at the same time.A music camp was ending Friday as the first work ..

Read more

Concrete Pour

June, 2018

Blog Post It was a very spectacular yet quiet weekend at the camp this Memorial Day. No work crews were scheduled, but the planning for the weekend of June 2 was in full speed mode. The weather outlook is pretty good today with temps in the mid 70’s and a slight chance for showers.  ..

Read more

Building Pads Prepared

May, 2018

5/23/18 – Bldg Pads and Grading Last week the building pads were staked out, leveled and on Saturday the concrete forms were started. The excavating crew also did some additional wok around the main building to improve drainage and provide additional outdoor seating for meals.  ..

Read more

Phase Two Begins

May, 2018

May 2018 – Phase II Kicks Off Summer has arrived early here in the North Country. We had no real spring, as the ice left Stony on April 30 and a week later temps were in the 70’s. To quote a famous Prophet from the UP ‘We wait all summer for the snow to come so it’s kinda sad to see it ..

Read more

Final Push

April, 2018

Final Push The last portion of March and into the first half of April saw a major scramble to bring all the final elements together in preparation for the opening of Ministers Camp. Upstairs made ready for carpet The dining room ceiling tiles were installed  ..

Read more

Open Kitchen and AV equipment

April, 2018

3/30/18 Kitchen and AV Equipment The last week of March saw delivery and installation of kitchen and Audio/Visual equipment. Upstairs the remaining furniture was removed and lights installed. Kitchen Equipment brought in Food Prep Island Hand wa ..

Read more

Flooring and Doors

March, 2018

Flooring and Sealing Logs 3/20/2018 Another flurry of activity over the past 10 days has seen new activity upstairs as the lower level floors were finished. In the dining room, the new window sills are being installed. Window Sill The floor finishing on the lower level was in t ..

Read more

Painting Started and Hood Installed

March, 2018

Painting Started and Hood Installed March 2018 I’ve been traveling since the 7th, but the team has been hard at it, finishing up the ceiling grid work, hanging the range hood and they have started painting. The HVAC and electrical crews are spending a lot of time finishing up the ductwo ..

Read more

Serving Windows and Ceiling Grid

February, 2018

Serving Windows and Ceiling Grid The crews have been working on finishing up the sheet rocking and FRP installation over the past week. Progress was speedy and they were able to start on the installation of the roll shutter doors for the serving area and dish return windows.  ..

Read more

Upcoming Events

No events found.

SUBSCRIBE TO OUR NEWSLETTER

Receive promotions and news by email. Unsubscribe with one click.