Stony Lake Camp Renovation

Write something about your church here.

Interior Framing

January, 2018

Interior Framing Over the past ten days, there has been a major focus on interior framing. Good crew turnouts on the past two Saturdays have resulted in noticeable progress. The electricians are hard at it now, coming most evenings and the HVAC people are working during the days.  ..

Read more

Floor Trusses Are Set

January, 2018

01/12/18 Floor Trusses Set It was another cold and snowy Saturday, but a great crew showed up to complete the blockwork and start fitting the floor trusses. The door openings between the new sleeping rooms, the kitchen and dining areas were completed. Al Lake working on a s ..

Read more

Meeting

January, 2018

Camp Board & Crew Leaders meet for progress review I attended a meeting of the Stony Lake Camp/Renovation Committee and work crew leaders at Stony Lake Camp last night (Jan 4) on a cold and cloudless night. After a short walkthrough of the kitchen/dining construction area, they met i ..

Read more

Concrete Pour

January, 2018

Concrete poured The shortest day of the year was also one of the busiest as the important milestone of pouring the floor occurred. On Wednesday the plumbing inspection was completed and at 7 am the following day, the crew started backfilling the trenches and compacting the soil for the c ..

Read more

Upcoming Events

Jul 04, 2019

2019 LLC Summer Services

2019 LLC Summer Services July 4 – 7, 2019 Hosted by: Rockford Laestadian Lutheran Church LLC Property at Silver Sprin..

SUBSCRIBE TO OUR NEWSLETTER

Receive promotions and news by email. Unsubscribe with one click.