Stony Lake Camp Renovation

Write something about your church here.

Flooring and Doors

March, 2018

Flooring and Sealing Logs 3/20/2018 Another flurry of activity over the past 10 days has seen new activity upstairs as the lower level floors were finished. In the dining room, the new window sills are being installed. Window Sill The floor finishing on the lower level was in t ..

Read more

Painting Started and Hood Installed

March, 2018

Painting Started and Hood Installed March 2018 I’ve been traveling since the 7th, but the team has been hard at it, finishing up the ceiling grid work, hanging the range hood and they have started painting. The HVAC and electrical crews are spending a lot of time finishing up the ductwo ..

Read more